A map of environmental obligations for industry
Every business activity goes through the same sequence of obligations. This page helps you identify where your company stands today and decide which steps need to be taken first.
Compliance is more than an administrative requirement
Meeting environmental document and permit requirements is a condition for operating a business legally. Without an Environmental Approval, business licensing cannot be issued, and activities already underway risk being shut down.
What often happens is that a company handles one stage without knowing the next. As a result, costs are incurred twice, or facilities are already built to specifications that do not match the technical study that is later approved.
Understanding the whole process from the start keeps the work in the right order and avoids work that has to be redone.
Why choose us
- 01
Long-term, sustainable permits
Our services ensure your business's environmental permits remain valid for the long term, so you do not have to go through the trouble of obtaining environmental permits again and again.
- 02
Safe and compliant operations
We ensure your business operations run safely and in compliance with the law, for long-term business sustainability.
- 03
Financial impact from waste management
Our services optimize your business's waste management so that it is put to good use and delivers financial impact, both direct and indirect.
- 04
Certainty of processing time
Transparent progress tracking gives you certainty on when you can start legally compliant business operations.
- 05
Experienced team
Our experienced team is ready to improve the quality of your business's environmental studies, minimizing negative impacts while maximizing positive ones.
- 01Stage 1
Spatial Use Conformity Approval (KKPR)
Ensures that the location of the planned business and/or activity conforms to the spatial plan before the next approvals are processed.
KKPRSpatial use conformity approval. - 02Stage 2
Technical Approval
Provisions on environmental protection and management standards and/or traffic impact analysis. An application for an Environmental Approval must be accompanied by a Technical Approval.
View service- Wastewater discharge and/or utilization activities
- Emissions discharge activities
- B3 (hazardous and toxic) waste management activities
- Traffic impact analysis
Estimated duration
- Wastewater PERTEK
- 4–5 months
- Emissions PERTEK
- 4–5 months
- B3 Waste PERTEK
- 4–5 months
- Traffic Impact Analysis PERTEK
- 3–4 months
Technical ApprovalApproval from the central government or regional government. - 03Stage 3
Environmental Approval
An environmental feasibility decision or a statement of commitment to environmental management, which is a requirement for the issuance of business licensing or government approval.
View service- AMDAL
- UKL-UPL
- Detailed RKL-RPL
- DELH
- DPLH
Estimated duration
- AMDAL
- 6–12 months
- UKL-UPL
- 3–6 months
- Detailed RKL-RPL
- 3–6 months
- DELH
- 3–6 months
- DPLH
- 3–6 months
Environmental ApprovalA requirement for the issuance of business licensing or government approval. - 04Stage 4
Building Approval (PBG)
Approval to construct, alter, extend, or maintain a building in accordance with building technical standards.
PBGBuilding approval. - 05Stage 5
Operational Feasibility Certificate (SLO)
A statement that the business and/or activity meets environmental protection and management standards.
View service- Wastewater discharge and/or utilization activities
- Emissions discharge activities
- B3 waste management activities
Estimated duration
- Operational Feasibility Certificate (SLO)
- 3–4 months
SLOThe activity is ready to operate in line with environmental standards.
Once the activity is operating
Obligations continue for as long as the activity runs: periodic Environmental Approval implementation reports, and the Company Environmental Performance Rating Program (PROPER) assessment for businesses that meet the participant criteria.
Activities already operating without environmental documents
Not every company starts from Stage 1. Many activities have been operating for years before realizing that their environmental documents do not exist yet, or only find out when an inspection takes place. A remediation track is available for this situation.
- DELHEnvironmental Evaluation Document
- For activities whose scale requires an AMDAL but which are already operating without one.Estimated duration: 3–6 months
- DPLHEnvironmental Management Document
- For activities whose scale requires a UKL-UPL but which are already operating without one.Estimated duration: 3–6 months
Both documents stop administrative sanctions, restore the legality of the activity, and align the environmental management system with national standards, so the company can return to the normal compliance process.


Which stage is your company at now?
Tell us your type of activity and the documents you already have. We will help map out what is missing and what needs to be done first, free of charge for the initial review.