Compliance roadmap

A map of environmental obligations for industry

Every business activity goes through the same sequence of obligations. This page helps you identify where your company stands today and decide which steps need to be taken first.

Why it matters

Compliance is more than an administrative requirement

Meeting environmental document and permit requirements is a condition for operating a business legally. Without an Environmental Approval, business licensing cannot be issued, and activities already underway risk being shut down.

What often happens is that a company handles one stage without knowing the next. As a result, costs are incurred twice, or facilities are already built to specifications that do not match the technical study that is later approved.

Understanding the whole process from the start keeps the work in the right order and avoids work that has to be redone.

Why choose us

  1. 01

    Long-term, sustainable permits

    Our services ensure your business's environmental permits remain valid for the long term, so you do not have to go through the trouble of obtaining environmental permits again and again.

  2. 02

    Safe and compliant operations

    We ensure your business operations run safely and in compliance with the law, for long-term business sustainability.

  3. 03

    Financial impact from waste management

    Our services optimize your business's waste management so that it is put to good use and delivers financial impact, both direct and indirect.

  4. 04

    Certainty of processing time

    Transparent progress tracking gives you certainty on when you can start legally compliant business operations.

  5. 05

    Experienced team

    Our experienced team is ready to improve the quality of your business's environmental studies, minimizing negative impacts while maximizing positive ones.

  1. 01Stage 1

    Spatial Use Conformity Approval (KKPR)

    Ensures that the location of the planned business and/or activity conforms to the spatial plan before the next approvals are processed.

    KKPRSpatial use conformity approval.
  2. 02Stage 2

    Technical Approval

    Provisions on environmental protection and management standards and/or traffic impact analysis. An application for an Environmental Approval must be accompanied by a Technical Approval.

    View service
    • Wastewater discharge and/or utilization activities
    • Emissions discharge activities
    • B3 (hazardous and toxic) waste management activities
    • Traffic impact analysis

    Estimated duration

    Wastewater PERTEK
    4–5 months
    Emissions PERTEK
    4–5 months
    B3 Waste PERTEK
    4–5 months
    Traffic Impact Analysis PERTEK
    3–4 months
    Technical ApprovalApproval from the central government or regional government.
  3. 03Stage 3

    Environmental Approval

    An environmental feasibility decision or a statement of commitment to environmental management, which is a requirement for the issuance of business licensing or government approval.

    View service
    • AMDAL
    • UKL-UPL
    • Detailed RKL-RPL
    • DELH
    • DPLH

    Estimated duration

    AMDAL
    6–12 months
    UKL-UPL
    3–6 months
    Detailed RKL-RPL
    3–6 months
    DELH
    3–6 months
    DPLH
    3–6 months
    Environmental ApprovalA requirement for the issuance of business licensing or government approval.
  4. 04Stage 4

    Building Approval (PBG)

    Approval to construct, alter, extend, or maintain a building in accordance with building technical standards.

    PBGBuilding approval.
  5. 05Stage 5

    Operational Feasibility Certificate (SLO)

    A statement that the business and/or activity meets environmental protection and management standards.

    View service
    • Wastewater discharge and/or utilization activities
    • Emissions discharge activities
    • B3 waste management activities

    Estimated duration

    Operational Feasibility Certificate (SLO)
    3–4 months
    SLOThe activity is ready to operate in line with environmental standards.

Once the activity is operating

Obligations continue for as long as the activity runs: periodic Environmental Approval implementation reports, and the Company Environmental Performance Rating Program (PROPER) assessment for businesses that meet the participant criteria.

Special track

Activities already operating without environmental documents

Not every company starts from Stage 1. Many activities have been operating for years before realizing that their environmental documents do not exist yet, or only find out when an inspection takes place. A remediation track is available for this situation.

DELHEnvironmental Evaluation Document
For activities whose scale requires an AMDAL but which are already operating without one.Estimated duration: 3–6 months
DPLHEnvironmental Management Document
For activities whose scale requires a UKL-UPL but which are already operating without one.Estimated duration: 3–6 months

Both documents stop administrative sanctions, restore the legality of the activity, and align the environmental management system with national standards, so the company can return to the normal compliance process.

Technical drawing sheets spread across a desk

Which stage is your company at now?

Tell us your type of activity and the documents you already have. We will help map out what is missing and what needs to be done first, free of charge for the initial review.